How to install and test roller crusher in stone crushing plant ?
Source:www.greatwallcrusher.com Author:Great Wall Posted:2014-10-08 Views:
Roll crusher is mainly used for cement, construction, sand, refractories and other industries, which can crush medium hardness of various materials, such as ore, rocks, coke, coal, slag, refractory and cement clinker. Discharging granularity size range is adjusted from 0.5mm to 60mm. How to install and test run roll crusher? Great Wall Company stone crusher experts give us some of the following suggestions:
Roll crusher must be installed in cement basis with a certain intensity, the roll crusher foundation surface should be level ground and leave the discharge port in the middle. The practical is designed on basis of local geology and plant structures. We should check the spare parts of roll crusher before installation, you must check the sufficient machine parts , avoid the parts damage to determine the intact before installation.
Active roll section should be installed with the driven roller section after getting the level, according to the drawings for installation, the drive belt tension should be adjusted appropriately, each parts should be added clean lubrication oil. After all the roll crusher parts installation is finished, it should strictly check the fastening parts, bolts without loosening.
Before operating the machine, you must check the lubrication part, whether roller crusher in good lubrication. After starting roll crusher in stone crushing plant, it should do the normal run for one hour without loading , and then we can feed materials for stone crushers ,primary we feed little grain in crushing cavity, if there are nothing wrong with the roll crusher and crusher operators increase the feed rate until the full load in stone crushing plant.